For the previous assignment. You did a Gantt Chart. And now I need one page explanation of this Gantt Chart. You can pretend you are doing a presentation, and you have to explain this chart to your audience. What is it about? What is in this chart? What kind of information did it show to the audience something like this.
|
WBS | Task Description | Deliverables | Estimated Time | Resources |
1 | HTSA Project | No | 940 days | |
1.1 | Initialize and Conceptualize | No | 74 days | |
1.1.1 | Identify MOV creation core Team | No | 3 days | Project manager,sponsor |
1.1.2 | Arrive at MOV | No | 39 days | Project manager,sponsor |
1.1.3 | Alternative Identification and feasibility analysis | No | 30 days | Project manager,sponsor,system architecture |
1.1.4 | Deliverables: Business Case | Deliverable | 1 day | Project manager,sponsor |
1.1.5 | Client Approval of Business case | Milestone | 1 day | sponsor |
1.2 | Plan Project | No | 16 days | |
1.2.1 | Define Project Scope | No | 3 days | Project manager,sponsor,system architect |
1.2.2 | Deliverables: Create Scope Management Plan | Deliverable | 1 day | Project manager,system architect |
1.2.3 | Deliverable: Create Communication plan | Deliverable | 1 day | Project manager |
1.2.4 | Define Project Phases | No | 3 days | Project manager |
1.2.5 | Define Tasks | No | 3 days | Project manager,system architect |
1.2.6 | Estimate Budget and Schedule | No | 3 days | Project manager |
1.2.7 | Deliverable: Create Baseline Project Plan | Deliverable | 1 day | Project manager |
1.2.8 | Client approval on Baseline Project | Milestone | 1 day | sponsor |
1.3 | Execute Project | No | 792 days | |
1.3.1 | Kickoff meeting | Milestone | 1 day | Project manager,sponsor,system architect |
1.3.2 | Analysis | No | 23 days | |
1.3.2.1 | Current System Analysis | No | 7 days | BSA[50%],system architect[50%] |
1.3.2.2 | Plan requirements gathering | No | 1 day | BSA |
1.3.2.3 | Analyze Requirements | No | 10 days | BSA,system architect |
1.3.2.4 | Document Requirements | No | 2 days | |
1.3.2.4.1 | Deliverable: Prepare Requirements Spec | Deliverable | 1 day | system architect |
1.3.2.5 | Verify Adherence to MOV | No | 1 day | BSA,Project manager,system architect |
1.3.2.6 | Client Sign off | Milestone | 1 day | sponsor |
1.3.3 | Design | No | 145 days | |
1.3.3.1 | Create Architecture Document | No | 21 days | system architect |
1.3.3.1.1 | Sent out for review | No | 10 days | system Designer |
1.3.3.1.2 | Make Change to document | No | 6 days | system Designer |
1.3.3.1.3 | Architectural Review Meeting | No | 3 days | system architect,system Designer |
1.3.3.1.4 | Deliverable: Final Architecture Meeting | Deliverable | 7 days | system architect,system Designer |
1.3.3.1.5 | client sign off | No | 1 day | sponsor |
1.3.3.1.6 | Document Put into repository | No | 1 day | BSA,Project manager |
1.3.3.2 | Create Application Design Document | No | 42 days | system architect |
1.3.3.2.1 | Sent out for review | No | 20 days | system Designers |
1.3.3.2.2 | Make Changes to document | No | 12 days | system Designers |
1.3.3.2.3 | Application design review meeting | No | 6 days | system architect,system Designer |
1.3.3.2.4 | Deliverable: Final application design document | Deliverable | 14 days | system architect,Project manager |
1.3.3.2.5 | Client sign off | Milestone | 1 day | sponsor |
1.3.3.2.6 | Document Put into repository | No | 1 day | BSA,Project manager |
1.3.4 | Production | No | 480 days | |
1.3.4.1 | Set Up Cloud Platform | No | 97.5 days | Others |
1.3.4.2 | Coding | No | 331.5 days | system coders |
1.3.4.3 | Integrate Cloud and Code | No | 30 days | Others,system coders |
1.3.4.4 | Unit testing | No | 1 day | Testers |
1.3.4.4.1 | Identify bugs | No | 2 days | Testers |
1.3.4.4.2 | Fix bugs | No | 6 days | system Design |
1.3.4.4.3 | Test again | No | 1 day | Testers |
1.3.4.5 | Integration Testing | No | 1 day | Testers |
1.3.4.5.1 | Identify bugs | No | 2 days | Testers |
1.3.4.5.2 | fix bugs | No | 6 days | system Designers |
1.3.4.5.3 | Test again | No | 1 day | Testers |
1.3.4.6 | Client Sign off | Milestone | 1 day | sponsor |
1.3.5 | Functional Testing/QA | No | 110 days | |
1.3.5.1 | Identify Test cases | No | 19 days | BSA |
1.3.5.1.1 | Accept test cases | No | 1 day | BSA,system architect |
1.3.5.2 | Performance testing | No | 50 days | |
1.3.5.3 | User Acceptance testing | No | 35 days | Testers |
1.3.5.4 | Analysize Testing results | No | 4 days | BSA |
1.3.5.5 | Client, Business sign off | Milestone | 1 day | sponsor |
1.3.6 | Implementation | No | 34 days | |
1.3.6.1 | Create Implementation Plan | No | 1 day | system architect |
1.3.6.2 | Deploy Database | No | 7 days | system Designer |
1.3.6.3 | Deploy Software | No | 7 days | system architect |
1.3.6.4 | Install Server software | No | 3 days | system Designer |
1.3.6.5 | Install database | No | 3 days | system Designer |
1.3.6.6 | Populate database with production data | No | 1 day | system Designer |
1.3.6.7 | Install Application | No | 3 days | system architect |
1.3.6.8 | Production Acceptance test | No | 1 day | system architect,Project manager |
1.3.6.8.1 | Make Changes as required | No | 5 days | system Designer |
1.3.6.8.2 | Test again | No | 1 day | system architect,Project manager |
1.3.6.9 | Go Live | No | 1 day | Project manager,system architect |
1.3.6.10 | client sign off | Milestone | 1 day | sponsor |
1.4 | close project | No | 45 days | |
1.4.1 | Prepare final report | No | 5 days | Project manager |
1.4.2 | Evaluate and release resources | No | 39 days | Project manager |
1.4.3 | Final presentation and acceptance to the system | Milestone | 1 day | Project manager,system architect |
1.5 | Evaluate Project | No | 13 days | |
1.5.1 | Post Implementation review | No | 3 days | Project manager,sponsor,system architect |
1.5.2 | Lessons Learned | No | 7 days | Project manager |
2 | Evaluating MOV | No | 3 days |